About This Project

In Cruas power plant, the French teams have done the replacement of the lagging in all areas of the reactor building, with the exception of the vessel shaft and the RIC area and what was semi-encapsulated. All the lines have had the protect 1000S insulation replaced with fluff wool in the form of an insulating blanket.

 

 

Owner

EDF SA

Client

EDF SA

Executing Company

KAEFER WANNER S.A.S.

Time frame

2023 - 2024

Services
Insulation